|
This article originally provided by
The Washington Post
March 20, 2006
Multiple Layers Of Contractors Drive
Up Cost of Katrina Cleanup
By Joby Warrick
Washington Post Staff Writer
NEW ORLEANS -- How many contractors does it take to
haul a pile of tree branches? If it's government work,
at least four: a contractor, his subcontractor, the
subcontractor's subcontractor, and finally, the local
man with a truck and chainsaw.
If the job is patching a leaking roof, the answer may
be five contractors, or even six. At the bottom tier is
a Spanish-speaking crew earning less than 10 cents for
every square foot of blue tarp installed. At the top,
the prime contractor bills the government 15 times as
much for the same job.
For the thousands of contractors in the Katrina
recovery business, this is the way the system works -- a
system that federal officials say is the same after
every major disaster but that local government
officials, watchdog groups and the contractors
themselves say is one reason that costs for the
hurricane cleanup continue to swell.
"If this is 'normal,' we have a serious problem in
this country," said Benny Rousselle, president of
Plaquemines Parish, a hurricane-ravaged district
downriver from New Orleans. "The federal government
ought to be embarrassed about what is happening. If
local governments tried to run things this way, we'd be
run out of town."
Federal agencies in charge of Katrina cleanup have
been repeatedly criticized for lapses in managing the
legions of contractors who perform tasks ranging from
delivering ice to rebuilding schools. Last Thursday,
Congress's independent auditor, the Government
Accountability Office, said inadequate oversight had
cost taxpayers tens of millions of dollars, by allowing
contractors to build shelters in the wrong places or to
purchase supplies that were not needed.
But each week, many more millions are paid to
contractors who get a cut of the profits from a job
performed by someone else. In instances reviewed by The
Washington Post, the difference between the job's actual
price and the fee charged to taxpayers ranged from 40
percent to as high as 1,700 percent.
Consider the task of cleaning up storm debris. Just
after the hurricane, the Army Corps of Engineers awarded
contracts for removing 62 million cubic yards of debris
to four companies: Ashbritt Inc., Ceres Environmental
Services Inc., Environmental Chemical Corp. and Phillips
and Jordan Inc.
Each of the four contracts was authorized for a
maximum of $500 million. Corps officials have declined
to reveal specific payment rates, citing a court
decision barring such disclosures. But local officials
and businesspeople knowledgeable about the contracts say
the companies are paid $28 to $30 a cubic yard.
Below the first tier, the arrangements vary. But in a
typical case in Louisiana's Jefferson Parish, top
contractor Ceres occupied the first rung, followed by
three layers of smaller companies: Loupe Construction
Co., then a company based in Reserve, La., which hired
another subcontractor called McGee, which hired Troy
Hebert, a hauler from New Iberia, La. Hebert, who is
also a member of the state legislature, says his pay
ranged from $10 to $6 for each cubic yard of debris.
"Every time it passes through another layer, $4 or $5
is taken off the top," Hebert said. "These others are
taking out money, and some of them aren't doing
anything."
Defenders of the multi-tiered system say it is a
normal and even necessary part of doing business in the
aftermath of a major disaster. The prime contracts are
usually awarded by FEMA or other government agencies
well in advance, so relief services can be brought in
quickly after the crisis eases. These companies often
must expand rapidly to meet the need, and they do so by
subcontracting work to other firms.
The two federal agencies that administer most
disaster-related contracts, FEMA and the Army Corps of
Engineers, say the system benefits small and local
companies that do not have the resources to bid for
large federal contracts. At the top end, prime
contractors must be large enough to carry the heavy
insurance burdens and administrative requirements of
overseeing thousands of workers dispersed across a wide
area, agency officials say. They also note that
contractors have a legal right to hire subcontractors as
they need them.
"Our purview of a contract goes to the prime
contractor only," said Jean Todd, a Corps contracting
officer.
But watchdog groups that monitor federal contracting
say Katrina has taken the contract tiering system to a
new extreme, wasting tax dollars while often cheating
companies at the low end of the contracting ladder. In
some cases, the groups say, companies in the top and
middle rungs contribute little more than shuffling
paperwork from one tier to the next.
"It's trickle-down contracting: You're paying a cut
at every level, and it makes the final cost
exponentially more expensive than it needs to be," said
Keith Ashdown of the watchdog group Taxpayers for Common
Sense. "And in almost every case, the local people who
really need to be making the money are at the bottom of
these upside-down pyramid schemes."
The gap is particularly large for roof repairs. Four
large companies won Army Corps contracts to cover
damaged roofs with blue plastic tarp, under a program
known as "Operation Blue Roof." The rate paid to the
prime contractors ranged from $1.50 to $1.75 per square
foot of tarp installed, documents show.
The prime contractors' rate is nearly as much as
local roofers charge to install a roof of asphalt
shingles, according to two roofing executives who
requested anonymity because they feared losing their
contracts. Meanwhile, at the bottom of the contractor
heap, four to five rungs lower, some crews are being
paid less than 10 cents per square foot, the officials
said.
At least the prime contractors for roofing and debris
removal owned equipment that could be immediately
applied to the job at hand. In the world of Katrina
contracting, this has not always been the case.
For example, one company hired as an ice vendor owns
no ice-making equipment. Landstar Systems Inc., a $2
billion Florida company placed in charge of the bus
evacuation of New Orleans, is a transportation broker
that specializes in trucking and has no buses of its
own. In 2002, the company was awarded a $100 million
contract to provide emergency transportation services
for the federal government during major disasters. The
contract, which is administered by the Federal Aviation
Administration, was expanded in the fall to a maximum
$400 million. Landstar declined a request for an
interview.
Thousands of New Orleanians had been stranded in the
Superdome for more than 48 hours by the time FEMA issued
the first order for a bus evacuation early on the
morning of Aug. 31. The order was passed to Landstar,
which then turned to other companies to locate buses,
according to an official chronology prepared by the
Department of Transportation. Landstar hired Carey
International Inc., of Washington, which then hired the
BusBank, of Chicago, and Transportation Management
Systems of Columbia, Md. Bus Bank and TMS called private
charter-bus companies -- some from as far away as
California and Washington state -- asking them to send
buses and drivers to New Orleans.
More than 1,100 buses eventually responded, some
arriving four days later, after traveling hundreds of
miles. Daily earnings averaged about $700 per bus,
according to bus company owners. Landstar's daily
earnings were nearly $1,200 per bus, government records
show.
"A lot of that money is going to brokers who didn't
have to do anything," said Jeff Polzien, owner of Red
Carpet Charters, an Oklahoma bus company that sent
coaches to New Orleans as a fourth-tier subcontractor.
Lower pay is hardly the worst problem subcontractors
face. With many tiers to navigate, money trickles down
slowly, delaying payment by weeks and months, and
frequently imposing hardships on the smallest firms.
Several bus company owners said they were still owed
tens of thousands of dollars for work they did in the
fall. For some, the delays have been ruinous.
Thomas Paige, owner of Coast to Coast Bus Line of
Dillon, S.C., laid off staff, and two of his four buses
were repossessed by creditors after payment for his New
Orleans work fell behind by three months.
"I went to New Orleans to help people -- and
hopefully to help myself -- but now I feel like I've dug
a ditch and fallen into it," Paige said. "If I would
have known what I know now, I never would have gotten
involved. It's just not worth it."
© 2006 The Washington Post Company
|